By Ramon Dacawi
BAGUIO CITY -- Most of the city’s
infrastructure projects supported by its Internal Revenue Allotment and Local
Development Fund are ahead or on schedule, city engineer Leo Bernardez reported
last week.
Out of 45 projects, Bernardez
said 17 were ahead of schedule, nine were on schedule, five were completed,
nine have been suspended and only one was behind schedule.
Ahead of schedule included the
construction of cross-drain and concrete canal at Chroime St., Upper Quezon
Hill amounting to P271,000; improvement of road at East Quirino Hill (P1.398
million; retrofitting of scoured foundations of the elevated sewerline along M.
Roxas Creek (P2.3 million); concret6ing of perimeter road and construction of
main gate at the city sewage treatment plant at North Sanitary Camp (P1.75
million); and rehabilitation of sewerline at Gray’s Compound to Sumulong St.,
Holy Ghost Barangay (P530,953).
Among those on schedule were
construction of covered drainage canal at Purok 4 of Fairview Barangay
(P169,800); drainage canal rehabilitation at Fairview (P149,689); continuation
of pathway at Purok 7, Irisan Barangay (P99,736); riprap and railings at San
Luis Village (P180,000); and improvement of multi-purpose basketball court at
Outlook Drive Barangay (P313,064).
A P3.394 million project
for the installation of sewerline at the back of the city sewage treatment
plant and rehabilitation of sewerline at North Sanitary Camp was suspended last
Feb. 25 pending the approval of a continuous project covering the two sites.
Also suspended was the
installation of additional sewerline from Dagohoy St. to T. Alonzo St.
amounting to P2.2 million pending issuance of a permit from the Department of
Public Works and Highways.
Likewise suspended pending a
change in work order were the restoration of eroded riprap wall at Atok Trail
Barangay amounting to P1.2 million, and the development of a drainage canal at
PurokOngasan, Loakan Proper amounting to P149,946 due to resistance of
residents.
Completed were improvement of
pathway and footbridge with railings at Purok II, Fairview (P74,800);
construction of drainage and canal at Purok 5 of Upper Market (P132,694);canal
concreting and upgrading of alley at Purok 6, Honeymoon-Holy Ghost (P345,000);
flood control concreting and upgrading of canal and alley at Purok 2 and 3 of
Honeymoon-Holy Ghost (P315,084); and relocation of sewerline at Lualhati
Barangay (P98,000).
No comments:
Post a Comment