BANAUE, Ifugao -- The 4.9-km Viewpoint-San Fernando farm-to-market road project here has hit a significant milestone, as work is now about 52.29 percent completed as of May 5.
The road is set to boost trade and business here once finished due to faster mobility of local folks.
Implemented under the Dept. of Agriculture’s Philippine Rural Development Project (DA-PRDP), the FMR subproject costs P124.8 million from the World Bank (loan proceeds), the national government through the DA, and local government of Banaue.
Engineer Edwin B. Camhit, PRDP rural infrastructure engineer said construction crews have almost completed excavation and widening of the road including 19 stations of stone masonry slope protection, two retaining walls and installed five cross drainages.
“More than one kilometer of the designed two-lane FMR at the end part of the subproject was already concreted,” said Camhit.
He identified other
ongoing construction works such as correctional excavation to align the
roadway, stone masonry, and structural concreting of retaining walls.
Benefiting around 362
households or 1,841 individuals in barangay Viewpoint and San Fernando, the FMR
subproject intends to reduce transport cost from P200 to P25; reduce travel
time from two hours to 30 minutes; increase new agricultural area by 4.01
hectares; and decrease transport losses at an average of three percent for all
crops.
Meanwhile, the
subproject is set to be assessed in the upcoming World Bank Implementation
Support Mission (WBISM) to the DA-PRDP that is scheduled to commence on May 24,
2021.
Due to restrictions,
the WBISM will still be conducted virtually. A full-blown documentation of the
subproject is being conducted using available digital resources
(geo-videos/photos, Unmanned Aerial Vehicle (UAV), and cameras) to capture the
technical aspect of the FMR subproject as well as the emerging benefits and
impacts of the subproject to the community.