Expecting Boasaw waters before end of 2015
>> Sunday, July 12, 2015
HAPPY WEEKEND
Gina Dizon
SAGADA
Mountain Province -- Following the monitoring of the P36 million
Boasaw irrigation and domestic works project, Mountain
Province coordinator Beverly Pekas of the Cordillera Highland
Agricultural Resource Management Project (CHARMP)- Department of
Agriculture said waters shall be reaching the town not long before the end of
the year.
This is the distribution tank at Palidan, Bangaan specially built for the Boasaw waters for irrigation waters of Tanulong and domestic waters of Poblacion Sagada. |
This
irrigation and domestic waterworks project with a 200 percent plus
slippage rate has been going through stressful implementation; supposed
to have been completed but have not seen completion due to
bad engineering design, snags in tank construction and
issues in mainline tapping.
Said
project contracted by Cotabato- based FFJJ Construction was bid out December
2011 and implementation in February of 2012 with P18 million from the priority
development assistance funds (PDAF) of Sen. Teofisto Guingona 111 and P18
million from CHARMP. Implementation however was questioned by the Sangguniang
Bayan of 2012 because of the plan did not reach the intended 15 barangay
beneficiaries as it called for a redesign of the project.
Following
talks with the SB in 2012, Mayor Eduardo Latawan
said two 4-inch diameter pipes shall be
connected from the 6-inch pipe connected from the water
source. A request for extension was granted which began the waterworks August
2012 for the less than a year duration project with the addition of 2 million
pesos from the Bottoms up Budgetting (BUB) process for additional pipes to
reach intended 15 beneficiaries and redesign of tanks.
The
LGU however did not follow what the latter committed in this LGU-DA-CHARMP-FFJJ
project called Improvement of Buasao Irrigation System and
Construction of Tanulong Tribe Irrigators Association Water
Services where only one 4-inch pipe instead of two was connected
from the 6-inch pipe connected from the main Boasaw dam.
This
is now the subject of the redesigned flow of waters from the main source to
Palidan, Bangaan distribution tank with addition of pipes and construction of
three intake tanks from the main source to ensure the full flow of waters.
Engineer
Windel Baaten of CHARMP who monitored the project said volumes of water was
being wasted thus above recommendation to the LGU and the contracting firm to
correct this.
Following
monitoring of the redesigned project, Baaten said an 8-inch pipe had been
connected from the water canal connected from the 6-inch diameter pipe from the
main Boasaw dam two weeks ago.
The
rest of the suggestions remain to be seen as the months pass by -- from an
8-inch diameter pipe connected from the water canal gets connected to a 6 inch
pipe passing through the already constructed tunnel located within the common
grounds with Tubo, Abra.
From
the tunnel, a tank shall be built from where two 4-inch diameter pipes shall be
connected to another tank with a 4-inch diameter pipe laid out to the
Palidan distribution tank.
The
new design is meant to ensure waters shall not be wasted along the connections
on to the distribution tank at Palidan, Bangaan.
Earlier,
only one 4-inch diameter pipe was connected from the 6-inch pipe connected from
the Boasaw dam.
Expense
for the redesign of the water flow takes remaining 15 percent of the balance of
the P36 million fund.
With
200% plus slippage of the project, the project has not yet seen full
realization as noted in feasibility study to provide water to 15 barangays.
So
far, only the eastern barangays have tasted water for a very brief moment of
three months in the second quarter of 2014 after which the waters stopped
coming while irrigation waters consistently flowed with complaints from the
Tanulong folks that water is not enough.
Earlier
a 6-inch pipe was connected from the main source to the water canal with 6-inch
pipe passing through the tunnel constructed within the earlier questioned
territory of Tubo, Abra who questioned why no prior consent was secured
from them. From the tunnel, one 4-inch pipe was connected toPalidan with a 4-inch pipe leading to
Tanulong irrigation and a 2-inch pipe leading to eastern barangays. Two inch
pipes were also laid out to the Poblacion barangays .
The
waterworks project, as noted during a meeting with CHARMP and LGU officers
March this year does not accommodate pipes leading to homes but only to
identified public f aucets within clustered households.
Said
meeting held March this year talked about formation of barangay-based water
associations wherever waters come from and also talked about
metering consumption when Boasaw waters shall finally see realization in
town.
0 comments:
Post a Comment