P52.7 M Bontoc water system project probed
>> Thursday, June 26, 2014
By
Desiree Sokoken
BONTOC, Mountain Province – The Department
off Public Works and Highways is now investigating an unfinished P52.7 million
water project which should have eased water shortage of this capital town.
Acting on request of
Mayor Franklin Odsey, the DPWH Central Office sent two representatives from its
Internal Audit Service (IAS) to investigate the long delayed completion of
the Bontoc water system project shat started
in 2005 and set for completion in 2008.
On June 18, engineer
Bernadeth Betsy Uy and Remedios Arellano of the DPWH-IAS inspected different
phases of the project together with Odsey and Mountain Province Assistant
District Engineer Charles Sokoken.
The probe was in
response to letter-request of Odsey and resolution of the Sangguniang Bayan
sent to DPWH Secretary Rogelio Singson to re-evaluate the completed phases and
turn over the implementation of the uncompleted ones to the Bontoc Local
Government Unit.
Awarded to
Manila-based contractor AquaterraKonstrukt, the project should have installed a
pipe water system for the four central barangays of Bontoc to be sourced from
Barangay Bayyo.
It consisted of six
phases, but only three were completed.
The sixth phase, which
covers the installation of pipes to the main source in Mt. Tatamang in Bayyo,
was terminated in 2010 because of strong opposition from Bayyo residents.
The latter feared that
the project might result in the depletion of their source of irrigation.
The pipes were then
re-routed to a water source in Baybay, Talubin, after a successful negotiation
with Talubin residents.
Odsey said that the
time is ripe for an investigation into the project, as its completion would
bring relief to the residents of the four central barangays.
It would be an
additional water source, thus assuring an ample supply to consumers.
According to Sokoken,
main pipes from the reservoir in Pagturao in Bontoc Ili to the intake tank in
Baybay have all been laid out.
However, some fixtures
necessary before a hydro test can be conducted have not yet been installed by
the contractor.
Of the 52.7 million
allotted for the project, there is a balance of 11 million. But according to
the DPWH-IAS representatives, there is a need to establish that this balance
still exists.
“Part of our probe is
to get our hands into the documents showing the payments that were made to the
contractor. This will help us determine the amount to be turned over to the
Bontoc LGU, should Sec. Singson decide that such is the proper course of
action,” Uy said.
Odsey said he hoped
for a speedy resolution of the matter, since putting an end to the water
problem in Bontoc is one of the priorities of his administration.
0 comments:
Post a Comment