Sagada road works defective; contractor urged to comply
>> Monday, October 27, 2014
By Gina Dizon
SAGADA, MOUNTAIN PROVINCE - Remove and replace road works along the
Dantay –Sagada road await completion with construction companies not having
fully complied with instructions of the Department of Public Works and Highways
(DPWH) to replace defective road works to ensure quality construction along the
span of the national road.
Assistant Engr Frank Jose of the quality assurance section of the
Mountain Province District Engineering office (MPDEO) said KVC construction has
not initiated any road repairs along the stretch of a 17 million project along
said national road despite instructions.
Despite uncorrected road defects, Benguet-based KVC is currently doing
another 7 million peso project constructing a gabion below the road after
Dapdapanan sitio along with widening works to be finished before the year
ends.
The 82 million works on upgrading and rehabilitation of road
sections spanning some 4 kilometres of road length from the regular funds of
the MPDEO have been programmed since 2011 and contracted by 3 construction
companies including Baguio-based BLC construction. A total of 181 million
have already been programmed and contracted out to cover a 9 kilometer
section of the total 13 kilometer Dantay-Sagada road since 2010.
An initial 48 million peso joint venture contract after the Dantay
junction was worked on by BMK-ETLatawan Construction in 2011. ET Latawan
Construction registered in the name of Engineer Eduardo Latawan Jr, the
current mayor of the town since 2007 is now represented by his wife
Felicitas Latawan as the registered contractor.
Tarlac-based BMK construction has already performed some 100 meters of
remove and replace works along intermittent road sections including the
application of epoxy on some cracks on the pavement on its 28 million peso
project with the DPWH.
Asked why the intermittence of road sections requiring remove and replace
methods, Jose said this must have been due to uneven
application of water to a mix with cement or there must have been a
pouring of rain on the constructed pavements further saying the
defects are 60% of human error and negligence rather than natural
causes.
Construction companies are the ones responsible to apply remove and
replace works on their contracted projects and the expense taken from the
contract cost. KVC and BMK construction have not fully collected the
contract cost from DPWH pending remove and replace works.
BLC construction which worked on a 37 million peso project on a 2
kilometer span of the road have fully performed remove and
replace works covering some 80 meters along some sections of said
road, Jose said.
Assistant District Engineer Charles Sokoken said validation of the
already done replacement works shall be conducted by the regional DPWH office.
In the same development, the PhP7 million project covering
some 280 meters from Dapdapanan sitio to the water-drenched
and curved section face road –right- of way issues with the owners
of adjacent lots demanding slopes to be
stonewalled.
Programmed to be finished December this year, the road section underwent
an earlier 5 million peso contract with a gabion constructed below the road with
cost from the maintenance funds of MPDEO.
BLC Construction is currently doing a 34 million peso road project
with DPWH along the main Antadao road.
An earlier work done along the sinking road section in Antadao shall be
worked on in another project by a separate construction company.
Meantime, a 7 million peso rehabilitation project is currently being
worked on by Bentrix construction involving the blasting of limestone rocks
along the road in Antadao covered by a certificate of non coverage (CNC) issued
by the regional Environment and Management Bureau of the Department of
Environment and Natural Resources (DENR) with instruction that said road work
“shall not exempt the grantee (MPDEO) from compliance with applicable
environmental laws.”
0 comments:
Post a Comment