RDC presses P72-M works on Ifugao General Hospital
>> Thursday, July 4, 2019
By Marlo
Lubguban
BAGUIO CITY – The regional project monitoring committee
headed by National Economic Development Authority-Cordillera regional director
Milagros Rimando and Dept. of Health regional director Amelita Pangilinan
agreed to conduct a third-party assessment of the structural retrofitting done
on the main building of the Ifugao General Hospital in Lagawe during a
problem–solving session of RPMC here on June 18.
The staff of Dept. of
Public Works and Highways Cordillera and structural engineer Joselito Buhangin
agreed to assist the regional DOH in the assessment.
The meeting was an
offshoot of the April 2019 site inspections by the RPMC on the carbon fiber
retrofitting the main hospital building in Lagawe.
RPMC member and RDC private sector representative Julie Cabato urged an additional third-party assessment to ensure the hospital will be structurally safe for use of the people of Ifugao.
Buhangin engineer attended the meeting on June 18 to provide his insights on the Ifugao General Hospital project and said while the presented building plan looked to be in order, he wanted to see the original calculations made in 2009 and the subsequent calculations for retrofitting to determine where the lapses and deficiencies were made.
RPMC member and RDC private sector representative Julie Cabato urged an additional third-party assessment to ensure the hospital will be structurally safe for use of the people of Ifugao.
Buhangin engineer attended the meeting on June 18 to provide his insights on the Ifugao General Hospital project and said while the presented building plan looked to be in order, he wanted to see the original calculations made in 2009 and the subsequent calculations for retrofitting to determine where the lapses and deficiencies were made.
He added that carbon
fiber retrofitting is a good option because of it being lightweight and
low-cost.
He added there are other options for retrofitting such as
column retrofitting, or jacketing using steel angles, steel plates, or concrete.
Buhangin said in
choosing a retrofitting method, certain criteria must be considered such as
current status and performance of the structure and performance required of the
structure after retrofitting, conditions for retrofitting construction works
and ease of maintenance and economy.
Regional office of DPWH was asked by DOH to assess the main building with Buhangin.
Regional office of DPWH was asked by DOH to assess the main building with Buhangin.
The results of the
assessment will be the basis of whether or not to proceed with Phase III of the
Ifugao General Hospital project, amounting to 72 million pesos.
Phase III consists of
site preparation, masonry work, grouted riprap, tile works, railings, doors
& windows, plumbing, and structural trusses.
The Ifugao General
Hospital project is part of the DOH Health Facilities Enhancement Program
(HFEP) aimed to replace the previous Ifugao General Hospital situated in
Kiangan, Ifugao.
0 comments:
Post a Comment