DPWH: Stop contracts over 3 Apayao roads; RPMC urges extension
>> Saturday, January 18, 2020
By Marlo Lubguban
LUNA, Apayao – The Apayao 1st District Engineering Office of the Dept.
of Public Works and Highways issued notice to provincial contractors to
terminate their contracts over three vital road projects for delay in their
implementation among other problems.
Apayao DEO head engineer Albert Gahid said he had
issued the notices. But in Baguio City, the Cordillera Regional Project
Monitoring Committee (RPMC), led by National Economic Development
agency-Cordillera regional director Milagros Rimando recommended to Gahid that
contractors be given time extension to complete the projects.
The RPMC gave recommendations on the three Apayao road projects during
its meeting in Baguio.
These projects have been flagged under the Regional
Project Monitoring Evaluation System for incoming delays.
Two of the projects, Manag-Talifugo-Paddaoan and
Manag-Liwan roads, are in Conner while another, Bulu (Lenneng) road, is in
Kabugao. These roads connect various industries and tourist sites in Apayao.
The Manag-Talifugo-Paddaoan road, in particular,
connects Conner’s banana, coffee, cacao, rice and corn industries to the
Tabuk-Conner-Kabugao National Road.
The Manag-Liwan road leads to the declared tourism
destinations of Purag River, Purag Cave, and Bellang Cave in Conner, Apayao.
The Bulu (Lenneng) road will improve access to the
Gulolan Falls in Paco Valley, Kabugao, Apayao.
The RPMC previously inspected the three project
sites on Nov. 27 and 28, 2019.
The delays were attributed primarily to bad
weather.
The Manag-Liwan road was also delayed due to a
right-of-way concern with an elementary school.
The school’s existing stage and comfort room are in
the way of the road project.
The RPMC urged negotiation with concerned school
and barangay to demolish and rebuild the structures and construct a retaining wall
to keep the students safe.
It was agreed in the meeting that DPWH will include
a timeline in their project reports to indicate realistic targets allowing some
for revisions or extensions.
The regional Dept. of Environment and Natural
Resources also offered to assist DPWH implement environmental policies as two
of the projects are access roads to tourist destinations.
The RPMC monitors government projects region-wide
to ensure on-time implementation by facilitating the resolution of project
issues.
The committee conducts inspections, problem-solving
sessions, trainings, and quarterly meetings to achieve its goal of proper
implementation of government projects.
It is composed of regional government agencies, the
local governments, and the private sector.
The RPMC had also nominated John Glenn Abela of the
United Architects of the Philippines to join RDC private sector representatives
Arnel Cabanisas and Dr. Julie Cabato as members of the RPMC.