Distribution firms blamed for power crisis in Phl
>> Friday, July 11, 2014
By
Dexter A. See
BAGUIO CITY – The failure of private
distribution companies and electric cooperatives to enter into power supply
contracts with power plant investors for the timely put up and operation of new
power plants in the different parts of the archipelago is the primary culprit
for the previous power crisis in Visayas, the on-going power crisis in Mindanao
and the projected severe power crisis in Luzon by 2016, a power industry expert
said here June 29.
Prof. Rowaldo del
Mundo, associate professor of the University of the Philippines – National
Engineering Center (UP-NEC), said it would be unfair to totally blame the
government for previous and upcoming power shortages in the different parts of
the country because it is not their obligation to enter into power supply
contracts as the Electric Power Industry Reform Act (EPIRA) mantes the
distribution utilities to be the ones to secure their respective power supply
contracts that would cater to their respective power demands for a certain
duration of time.
“Since the
implementation of the EPIRA over 13 years ago, there was only one new power
plant that was built for still unknown reasons.” Del Mundo stressed, referring
to the 600-megawatt clean coal power plant of GM Corporation in Mariveles,
Bataan, which was officially commissioned sometime in February this year.
Del Mundo said “it is
the obligation of the distribution utilities to contract out their projected
power requirements to serve as basis for investors and financial institutions
to infuse the needed capital in order to put up new power plants that will
prevent the occurrence of power crisis in the different grids.”
In the case of Visayas
which suffered from a power crisis in 2008, the UP professor explained
distribution companies waited for the power shortage before realizing the need
to commission new power plants that eventually solved the possible prolonged
power outages that could have been detrimental in the island’s robust economic
growth over the past several years.
For Mindanao, del
Mundo added the island will continue to suffer from prolonged rotating
brownouts that could increase from 188 days per year this year to around 250
days next year once no new power plants will be operational, citing that
“peaking power plants” such as diesel-fired power facilities will help address
the problem but not in terms of lowering the power rates being charged to the
consumers in the area.
In the case of the projected
severe power crisis in Luzon, del Mundo said the distribution utilities,
particularly Meralco that accounts for at least 75 percent of the power demand
in the grid, have failed to secure their power supply contracts that would
address their power requirements in the future, thus, no new power plants were
built for more than a decade now.
Del Mundo recommended
to the energy department to mandate all distribution utilities nationwide to
submit their respective forecasts of power demand in the next five years in
order to determine the available uncontracted power requirement which will be
then subjected to power supply contracts with prospective power investors to
allow them to work out the building of new and reliable power plants that would
solve the possibility of increased rotational brownouts detrimental to the
desired economic growth.
“For every one percent
increase in the country’s gross domestic product, there is also an increase of
around 1 percent of the country’s total power demand, thus, the need for the
continuous building of new power plants around the archipelago to help address
the additional power requirements caused by the improving economic situation,”
del Mundo said.
He said no power
generation investor was able to build new power plants previously because there
was no guarantee from the distribution utilities that a portion of the power
that they will produce will be bought by the companies considering the huge
investment required to put up a power plant.
For every megawatt of
power, he cited investors are required to infuse at least $1 million which
could only be acquired through the aid of financial institutions, thus, the
need for power distribution utilities to guarantee the purchase of the power to
be produced in order to make the construction and operation of power plants
feasible.
Del Mundo also
suggested to the power distribution utilities to undergo the public bidding of
their uncontracted power requirements so that they will be able to get the most
advantageous offers from interested power generation companies through the
least cost principle for them to be able to offer to their consumers lower
rates but quality and reliable power delivered to them in the future.
He lamented the
practice of Meralco over the past several decades of undergoing negotiated
contracts with power producers for their power requirements which makes it
difficult for the Energy Regulatory Commission (ERC) to decide on the viability
of the company’s power rates.
0 comments:
Post a Comment